USF PRESENTATION THEATER – SAN FRANCISCO – #595

This project consists of upgrading a historic, neo-Gothic theater with some new stage rigging, a new catwalk and some electrical improvements.

Status: Project bid out Structural Steel, Production Rigging, and Design-Build Electrical on 4/16/25. Construction expected from June 2025 – October 2025.

THE INTERNATIONAL SCHOOL (ISSF) – 150 OAK STREET – #594

This project includes a full renovation of the west wing of this private school (7 floors, 64,000 square feet) including structural work, new stairs and skylights, new HVAC systems, and upgraded interiors throughout. The eastern portion (6 floors, 111,000 SF) will be occupied during the school year. The project consists of six phases with a total of $64M.

Status: This project will take a rolling buyout approach. Phase 1A and 1B bid out in March 2025. The remaining phases will be bid out separately over the next six months as design progresses. Overall construction scheduled to start in June 2025 for a 14-month duration.

BERRYESSA STATION TOD AFFORDABLE HOUSING – SAN JOSE – #563

New construction of a ten-story, 202,071 gsf, affordable housing development in San Jose. Project is committed to Green Building and will be all electric, with PV and battery storage. Construction type is Type 1A.

Status: GMP set expected Q3 2025. Construction start anticipated Q1 2026.

TREASURE ISLAND PARCEL E1.2 – BEHAVIORAL HEALTH BUILDING – #571

New construction of a six-story behavioral health building on Treasure Island. Project will consist of 124 dormitory style units with shared bathrooms for a total of approximately 73,750 gsf. Construction type is still to be determined.

Status: The 95% CD Estimate took place in October 2024. GMP not expected until Q3 2025. Tentative construction start is April 2026 for a 19-month duration.

OUSD MELROSE LEADERSHIP ACADEMY – OAKLAND – #585

This project, a K-8th grade campus located in the Maxwell Park neighborhood, has a phased two year plus schedule starting in Q1 2026. Scope includes a new classroom building and renovation of the existing campus. Structural upgrades include extensive concrete FRP work.

Status: 100% Design Development budget took place in February 2025. Expecting bid to occur in Q3/Q4 2025. Construction would begin late Q1 2026.

SAN FRANCISCO (sf) TOWERS ENTRY EXPERIENCE – SAN FRANCISCO – #578

SF Towers is one of the premier senior living communities in the Bay Area, located on Pine St, between Van Ness and Franklin. The project consists of major upgrades of their first-floor auxiliary spaces and kitchen.

Status: A Conceptual Budget Estimate occurred in April 2024. The GMP will not take place until Q2 2026 at the earliest and construction will not commence until at least Q3 2026. Duration to be determined once official scope and phasing is pinned down but expecting it to be two phases for 12 to 15 months.

JFCS HOLOCAUST CENTER – SAN FRANCISCO – #577

The Holocaust Center is a dedicated program committed to the remembrance, research, documentation, and education concerning the Holocaust. The new building will replace an existing building at 2245 Post Street. It will include public exhibition space, a library, conference rooms, and state-of-the-art digital communications capability. We’re expecting the building to be about 35,000 SF, it will be a very challenging project due to a narrow lot and minimal staging areas.

Status: The extent of this project has expanded and is expected to go through a redesign for a larger site. New design drawings are expected Q2 2025. Construction is anticipated to start in Q2 2026.

3485 CESAR CHAVEZ – SAN FRANCISCO – #563

New construction of a residential building with five stories of Type IIIA construction (63,359 SF) over two stories of Type IA construction (23,249 SF). The ground floor will include residential service areas and common spaces, while the upper floors will house 126 residential units, consisting of 66 studios and 60 one-bedroom units.

Status: 100% Design Development budget took place in March 2025. CD stage expected Q4 2025. Construction start date anticipated for June 2026 for 21 months.

750 GOLDEN GATE – PHASE 2 – SAN FRANCISCO – #565

Phase 1 of this project is under construction. The two phases together include construction of a 171-unit, 8-story Type I, affordable family housing development. Construction includes the demolition of an existing parking lot. The building will include common areas and amenity spaces on the first floor. We are currently expecting an update on the timeline for Phase 2 and will have more information April 2025.

Status: Design Development budget for Phase 2 of this project is TBD.

1979 MISSION STREET – SAN FRANCISCO – #586 & #587

This project is a Cahill/Guzman joint venture. Located directly adjacent to the 16th Street BART station, this 2-3 phase project will consist of approximately 400 units. Design concepts are still being flushed out, but it will likely be a mix of high-rise and mid-rise buildings, 9 to 16 stories.

Status: Currently in the early schematic design phase. Final bid not expected until at least Q1 2026. Construction expected to start Q2 2026 for the first building.