Out Blog

750 GOLDEN GATE – SAN FRANCISCO

This is a sister project to 850 Turk. The site will be built in two phases, together providing construction of a 171-unit, 8-story Type I, affordable family housing development. Construction includes the demolition of an existing parking lot.  The building will include common areas and amenity spaces at the first floor. Phase 2 is expected to start one year after phase 1 begins.

Status: This project is being fast-tracked through design. Design Development Estimate took place in March 2024. Early Design-Build trades (Elevators, Fire Sprinklers, Solar/PV, and Tower Crane) are currently bidding with a Bid Due Date of April 5, 2024. GMP for remaining trades is slated for July 2024. Construction is expected to start by December 15, 2024.

850 TURK STREET – SAN FRANCISCO

This project is new construction of a 92-unit, 105,000-gsf, 8-story Type I, affordable family housing development.  Construction includes the demolition of an existing one-story parking garage.  The building will include common areas and amenity spaces at the first floor. 

Status: Select Design-Build and early trades bid out in 2023: Shoring, Ground Improvements, Structural Concrete, Exterior Building Maintenance, Elevators, Fire Sprinklers, Plumbing, HVAC, Electrical, Solar, and Crane scopes. The remaining trades are currently scheduled to bid out July 2024. Construction projected to start Q4 2024 for a 21.5-month duration.