SHERMAN RECOVERY CENTER – PLEASANT HILL – #2605
This project will deliver a 16-bed recovery and treatment facility that includes approximately 8,500 square feet of treatment space and 2,500 square feet of permanent supportive housing. It is a full Design-Build project.
Status: Design is underway, abatement and demolition have commenced, and construction anticipated to start Q1 2027. Demo, Abatement, and Design-Build MEP trades bid out in June and Earthwork and Site Utilities bid out in August. Remaining trades will bid in October 2026.