SHERMAN RECOVERY CENTER – PLEASANT HILL – #2605

This project will deliver a 16-bed recovery and treatment facility that includes approximately 8,500 square feet of treatment space and 2,500 square feet of permanent supportive housing. It is a full Design-Build project.

Status: Design is underway, abatement and demolition have commenced, and construction anticipated to start Q1 2027. Demo, Abatement, and Design-Build MEP trades bid out in June and Earthwork and Site Utilities bid out in August. Remaining trades will bid in October 2026.

SAN MATEO UNION HIGH SCHOOL DISTRICT CLASSROOM RENOVATIONS – PHASE 2 – SAN MATEO – #596

This is the second phase of a three-phase project enhancing 420 classrooms across 6 high school campuses in the San Mateo School District. Scope will include new paint, ceiling tile, lights, markerboards and limited audio-visual work. The anticipated schedule is that this 2nd phase of the work will be completed over Summer 2027.

Status: The GMP bid is slated for late October / early November 2026 with construction starting in June 2027. 

THE BRANSON SCHOOL GYMNASIUM RENOVATION – PHASE 2 – SMALL GYM – ROSS (MARIN COUNTY) – #598

This project includes new construction and renovation of the Branson School’s existing gymnasium complex. The school is situated on a beautiful 17-acre property in Ross, CA, near Mt. Tamalpais in the North Bay. The scope includes two gym updates and a total renovation of locker rooms, training rooms, an added cardio area, and elevator replacement. The area of the building is approximately 19,000 sf. There is very limited site work, some restriping and small added site concrete pad.

Status: Phase 2 (Small Gym & Core Building) GMP is slated for October 2026. Phase 2 construction expected to start in February 2027 for a 7-month duration.

LAGUNA HONDA AFFORDABLE SENIOR HOUSING – SAN FRANCISCO – #545

This is a Cahill/Guzman joint venture. New construction of a 159-unit Senior Housing building.  Project will also include Health Services, Senior Center, Home Health Services and Early Child Childcare Education center. Development is located on the site of and adjacent to the Laguna Honda Hospital in San Francisco. (This project used to be 2 phases/buildings and now is planned to be a single building.)

Status: Conceptual budget took place in November 2025 and project is currently transitioning into the Schematic Design phase. The overall preconstruction/design schedule is pending, with DDC, EBM, Elevators and Design Build MEPS trades early bidding (and all other trades budgeting) in Q4 2026.