NEW ASIA SENIOR HOUSING (772 PACIFIC) – SF – #567

This is a Cahill/Pilot Construction joint venture. New construction of a 15-Story, 140,000 gsf, 175-unit affordable senior housing development with Type I over one Level Basement. The project includes a banquet hall & kitchen, community room, offices, outdoor terrace and roof deck in the non-residential areas.

Status: 50% DD Budget and Early Design-Build Trades bid out in Q3 2025: Dewatering, Shoring, Prefabricated Exterior Skin Alternate, EBM, Signage, Elevators, Fire Sprinklers, MEPS, and Tower Crane. GMP slated for Q4 2026 and construction not expected until Q1 2027.

NORTH FIRST STREET – SANTA CLARA – #593

The project is currently in the early conceptual design phase and is apt to include four separate buildings, with phased construction. This construction will likely include multiple affordable housing types (Senior, Family, Permanent Supportive Housing).

Status: Project currently in early conceptual design. Final bid expected in Mid-Late 2027. Approximate construction start set for late 2027/early 2028.

750 GOLDEN GATE – PHASE 2 – SAN FRANCISCO – #565

Phase 1 of this project is under construction. The two phases together include construction of a 171-unit, 8-story Type I, affordable family housing development. Construction includes the demolition of an existing parking lot. The building will include common areas and amenity spaces on the first floor.

Status: 750 Golden Gate Phase 2 Design Development budget for Phase 2 of this project is TBD. Construction is expected to begin in December 2026.

LAGUNA HONDA AFFORDABLE SENIOR HOUSING – SAN FRANCISCO – #545

This is a Cahill/Guzman joint venture. New construction of an approximately 160-unit Senior Housing building.  Project will also include both an adult day health facility and early childcare education center. Development is located on the site of and adjacent to the Laguna Honda Hospital on in San Francisco. (This project used to be 2 phases/buildings and now is trending towards being a single building.)

Status: Project is emerging from being on hold for two years and is currently transitioning into the Schematic Design phase. The overall preconstruction/design schedule is pending.

ELLA ROHLFF’S PLACE – SAN FRANCISCO – #558

This project is new construction of a 94-unit, 71,600-gsf, 5-story Type IIIA over 2-story Type IA, affordable senior housing development.  Construction includes the demolition of an existing one-story plaza.  The building will include common areas and amenity spaces as well as a seating nook and laundry on every floor.  A new landscaped outdoor courtyard will connect the new building to the existing senior building directly adjacent, St. Mark’s Urban Life Center.

Status: An estimate for the 50% CD drawings took place in April 2023. Project is on hold.

BALBOA RESERVOIR BLOCK F – SAN FRANCISCO – #561

New construction of a seven-story, 190,000 gsf, 159-unit educator housing development, including a basement. Building will be seven Type I levels. The ground floor includes a main lobby, co-working spaces, fitness, offices, bike parking, dog wash, maker space etc. The basement garage provides public and residential parking, partially in mechanized lifts. The upper floors contain a mix of studio up to 3-bedroom residential units.

Status: Structural Concrete scope bid out as an early trade. This project has been delayed indefinitely. No new timeline provided.