The site includes two buildings that will be phased construction. The West Building will be constructed first to provide parking for the residence, which is 7-story building over basement/parking, 161 units, and approx. 220,730 g.s.f.  The East Building will be a 12-story high-rise building, likely mass timber, 107 units, and approx. 126,500 g.s.f. The overall duration will be 36 – 42 months of construction, depending on the overlap of construction between phases. The project is slated to start Q3 2026.

SD budgeting scheduled to occur Q1 2025, and bidding tentatively expected Q1/Q2 2026.