This project includes new construction and renovation of the Branson School’s existing gymnasium complex. The school is situated on a beautiful 17-acre property in Ross, CA, near Mt. Tamalpais in the North Bay. The scope includes two gym updates and a total renovation of locker rooms, training rooms, an added cardio area, and elevator replacement. The area of the building is approximately 19,000 sf. There is very limited site work, some restriping and small added site concrete pad.

Status: Phase 1 (Large Gym Renovation) construction completion expected in July 2026. Phase 2 (Small Gym & Core Building) GMP bid is slated for September 2026. Phase 2 construction expected to start in February 2027 for a 7-month duration.