New construction of a 223,000-s.f., 176-unit, affordable housing development. The structure is composed of five levels of light gauge metal stud framing over two levels of Type I concrete. The site includes a modest amount of landscaping and hardscape around the perimeter of the building.

Status: The Metal Stud Framing & Drywall, Elevators, Fire Sprinklers and PV Panels bid out in April 2022 with the 100% DD set of plans.  The balance of the trades is expected to bid out in Q3 2023.  The estimated start date of this project is December 2023.