This is a joint venture project with Guzman Construction. New construction of a nine-story, 102,000 gsf family housing building. The all Type I concrete structure will be 85-units: a mix of studio and up to 3-bedroom units. The ground floor includes a main lobby, offices, a multipurpose room, bicycle parking, and building services. No vehicle parking is included.
Status: Five early design-build trades bid out in October 2022 and May 2023: Auger Cast Piles, Exterior Building Maintenance, Fire Sprinklers, Solar PV, and Tower Crane. Early trade MEPs, Structural Concrete, Earthwork, Elevator, Shoring, Joint Trench & Temporary Power set to bid in Q4 2024 and GMP for the balance of the trades is estimated to take place Q1 2025. Construction expected to begin Q2 2025 in current schedule for a 22-month duration.