This project is a two-phase renovation of the Branson School’s existing gymnasium. The school is situated on a beautiful 17-acre property in Ross, CA, near Marin in the North Bay. The scope includes two gym updates and a total renovation of locker rooms, training rooms, an added cardio area, and elevator replacement. The area of the building is approximately 19,000 sf. There is very limited site work, some restriping and small added site concrete pad. Phase 1 is for the large gym only and will have a Summer 2026 start. Phase 2 consists of the remaining scope that will begin Summer 2027.
Status: A Schematic Design estimate occurred in August 2025. The GMP bid for Phase 1 is slated for October/November 2025 with construction set to begin February/March of 2026 for 7 months. Phase 2 is still in the budgeting phase.