MARIN ART & GARDEN CENTER – ROSS (#700)

The Marin Art & Garden Center Phase 1A – Sowing the Seeds Project includes renovations and refurbishment of the Celebration Area, Livermore Pavilion, and Northgate Buildings. The Livermore Building will be expanded to include a new restroom and storage area plus an auxiliary storage building. Additional scope includes surrounding deck, landscape, utility, and relocation of the rose garden to the main entry. MEP scope includes a new electrical service, new mechanical, new restrooms and expanding the existing fire sprinkler system.

Status: The following early trades bid out in October 2025: Fire Sprinklers, Plumbing, HVAC, and Electrical. 100% DD Budget also took place during this time. Expecting GMP bid to occur in Q1 2026. Construction would begin in March 2026.

OUSD MELROSE LEADERSHIP ACADEMY – OAKLAND – #585

This project, a K-8th grade campus located in the Maxwell Park neighborhood in Oakland, has a phased two-year schedule starting in June 2026. Scope includes a new classroom building and renovation of the existing campus. Structural upgrades include extensive concrete FRP work.

Status: Expecting GMP bid to occur in mid-January 2026. Construction would begin in June 2026.

1979 MISSION STREET – PHASE 2 – SAN FRANCISCO (#587)

This project is a Cahill/Guzman joint venture. Located directly adjacent to the 16th Street BART station, Phase 2 Family Housing will consist of a 16-story Type 1A high-rise (Parcel 2) and 9 story Type 1A mid-rise (Parcel 3) with a combined 246 Family Housing units.

Status: Budgeting for the schematic design is underway for both parcels. Early trade bid (DD) for the high rise is expected in Q1 of 2026, with the balance of GMP bidding in Q4 2026 for a start of construction in Q2 of 2027. Parcel 3 mid-rise early bidding (DD) in Q2 of 2027, balance of GMP bidding in Q4 of 2027 for a construction start Q2 of 2028.