This project includes a full renovation of the west wing of this private school (7 floors, 64,000 square feet) including structural work, new stairs and skylights, new HVAC systems, and upgraded interiors throughout. The eastern portion (6 floors, 111,000 SF) will be occupied during the school year. The project consists of six phases with a total of $64M.

Status: This project will take a rolling buyout approach. Phase 1A and 1B bid out in March 2025. The remaining phases will be bid out separately over the next six months as design progresses. Overall construction scheduled to start in June 2025 for a 14-month duration.