The project includes the demolition of all non-historic buildings, structures, and caging on the existing WildCare property, the relocation and restoration of the historic Terwilliger building and construction of new three-story building and caging on the existing site. The project replaces existing outdated, undersized facilities with new, code compliant animal hospital, educational, and animal housing facilities. The project also includes replacement of the existing pedestrian bridge over San Rafael Creek, along with creek mitigation as required along the section of creek fronting the property.

Status: All remaining trades bid out in December 2024 and are pending award confirmation. Construction scheduled for March 2025 for a 15.5-month duration.